You are here:
Home » News & Info » District Projects
Recently Completed Projects
Supplemental Water Project – Nipomo Area Pipeline Improvements, Southland Extension
- Completed November 2020
- R. Baker Inc. and Unified Field Services Corporation
- $3,553,360
2017 Utility Adjustment Project
- Completed November 2017
- R. Burke Corporation
- $197,720
Supplemental Water Project – Joshua Road Pump Station Reservoir
- Completed May 2017
- Pacific Hydrotech Corporation
- $2,702,423
- More info
Blacklake Water Reclamation Facility Headworks Rehabilitation Project
- Completed May 2017
- Cushman Contracting Corporation
- $192,528
Orchard Road Waterline Project
- Completed
- R. Baker Inc.
- $13,100
Nipomo Palms Lift Station Replacement Project
- Completed May 2023
- Brough Construction, Inc.
- Final Contract Amount: $866,827
OFFICE HOURS: Mon - Fri 8am - 4:30pm
24-HR PHONE: 805 929-1133
Emergency, after-hours service available
Regular Board Meetings are held the 2nd & 4th Wednesday at 9am
Branch Street Waterline Replacement Project
- Completed February 2024
- Raminha Construction, Inc.
- Final Contract Amount: $821,315
Southland Wastewater Treatment Facility Storage Building Project
- Completed September 2020
- PWS Construction, Inc.
- Final Contract Amount: $188,114
Blacklake Sewer System Consolidation Project Lift Station Improvements and Blacklake WRF Decommissioning
- Estimated completion: November 2025
- Budgeted: $6,641,475
- Scope of Project:
- Construction of approximately 700 feet of gravity sewer
- Construction of approximately 400 feet of force main
- Construction of Blacklake Lift Station
- Decommissioning the Blacklake WRF
- Construction of replacement lift station for the existing Woodgreen Lift Station
2024 Water Distribution System Improvements
- Estimated completion: June 2025
- Budgeted: $2,019,261
- Scope of Project:
- Construction of approximately 4,300 linear feet of 12-inch water main on Pomeroy Road between Willow Road and Aden Way
- Construction of approximately 365 linear feet of 8-inch water main on Sea Pines Place between Via Concha and Woodgreen Way
- Construction of approximately 765 feet of 4-inch water main on Red Oak Way within the District’s service area.
Supplemental Water Project Interconnection Improvements
- Estimated completion: March 2025
- Budgeted: $1,195,200
- Scope of Project:
- Construction of vaults and piping at the Golden State Water Company Cypress Ridge interconnect site
- Construction of vaults and piping at the Woodlands Mutual Water Company interconnect site
Frontage Road Trunk Sewer Project
- Budgeted: $1,000,000
- Scope of Project:
- Replacement of approximately 4,700 linear feet of sewer line and 17 manholes on Frontage Road, between Division Street and Juniper Street.
Eureka Well site c.1980
Eureka Well Replacement Project
Quad Tank Disinfection System