FAQs
Invitation and Program for NSWP’s Joshua Road Pump Station Reservoir Ribbon Cutting on May 24, 2017 | Photos
Supplemental Water Rates – Effective December 1, 2017, the Supplemental Water Rates were eliminated as a separate rate and included in the bimonthly rates for water. Current rates can be found at ncsd.ca.gov/customer-services/rates-fee-schedules.
Information about Disinfection with Chloramines | Chloramines and Fluoridation Fact Sheet
Press Releases
Press Release: Supplemental Water has Arrived in Nipomo (7-10-2015)
Press Release: Board Authorizes Bidding for Supplemental Water Project Joshua Road Pump Station Reservoir (1-29-2016)
Press Release: Nipomo CSD Supplemental Water Project Receives Project of the Year Award (2-9-2016)
Press Release: Board Awards Contract for Supplemental Water Project Joshua Road Pump Station Reservoir (3-10-16)
Monthly Progress Reports
- June 2015 – Bid Package 4
- May 2015 – Bid Package 4
- April 2015 – Bid Package 4
- March 2015 – Bid Package 4; March 2015 – Blosser Road Water Main
- February 2015 – Bid Package 4; February 2015 – Blosser Road Water Main
- January 2015 – Bid Package 4; January 2015 – Blosser Road Water Main
- December 2014 – Bid Package 4; December 2014 – Blosser Road Water Main
- November 2014 – Bid Package 4; November 2014 – Blosser Road Water Main
- October 2014 – Bid Package 4; October 2014 – Blosser Road Water Main
- September 2014 – Bid Package 4; September 2014 – Blosser Road Water Main
- August 2014 – Bid Package 4
- July 2014 – Bid Package 4
- June 2014 – Bid Package 4
- May 2014 – Bid Package 4
Bid Packages
Bid Package 1 – Santa Maria River Crossing, Prequalified Contractors
Supplemental Water Project Joshua Road Pump Station Reservoir, Prequalified Contractors | Bid Summary
Concept Design Report (prepared by AECOM, dated April 2009)
Volume 1, Volume 2 and Volume 3
Environmental Impact Report (EIR)
2011 Addendum EIR, (prepared by Douglas Wood & Associates, Inc., dated April 25, 2012)
Narrative Report (prepared by AECOM, dated August 2009)
Comments on EIR
Final Environmental Impact Report (prepared by Douglas Wood & Associates, Inc. dated March 2009) The report is large and broken into parts.
- Part 1 (Pages I-1 to IV-6)
- Part 2 (Pages V-1 to V-53)
- Part 3 (Pages V-54 to V-86)
- Part 4 (Pages V-87 to V-109)
- Part 5 (Pages V-110 to V-144)
- Part 6 (Pages VI-1 to XI-57)
Other Documents
September 9, 2015 Ribbon Cutting Ceremony Program | Project Chronology | Pictures
Public Information Session Presentation – June 23, 2015
Draft Evaluation of Supplemental Water Alternatives – Technical Memorandum No. 1 Constraints Analysis (dated June 2007, prepared by Boyle Engineering)
Part 1 Part 2 Part 3 Part 4 Part 5
For the State Water Pipeline tap
Objectives of the Supplemental Water Pipeline (approved on April 12, 2006)
Waterline Feasibility Study-Santa Maria River Crossing Alternatives (prepared by Cannon Associates dated March 2005)
Memorandum of Understanding By and Between the City of Santa Maria and Nipomo Community Services District (dated September 2004)
Wholesale Water Supply Agreement between the City of Santa Maria and Nipomo Community Services District (dated January 1, 2010) SUPERSEDED BY AGREEMENT DATED MAY 7, 2013
Wholesale Water Supply Agreement between the City of Santa Maria and Nipomo Community Services District (dated May 7, 2013)